A factory produces toy cars. The number of workers n and the number of days d to complete an order are inversely proportional. An order takes 36 days with 5 workers.

(a)

How many days would it take 9 workers to complete the same order?

[2 marks]
(b)

Write the formula connecting n and d.

[2 marks]

Work this out on paper, then compare with the answer and worked solution below. With a free account you can submit written answers for marking.

Show answer

(a) 20 days

(b) n × d = 180 or d = 180/n

Common mistakes: using direct instead of inverse proportion

Show mark scheme and worked solution

Marking points

M1 (a) · 1 mark · Sets up inverse proportion relationship: n × d = constant.

A1 (a) · 1 mark · Finds correct number of days for 9 workers (20 days).

M2 (b) · 1 mark · States or derives connection between n and d.

A2 (b) · 1 mark · Writes correct formula, n × d = 180 or d = 180/n.

Worked solution

n × d = constant. 5 × 36 = 180. For n = 9, d = 180/9 = 20 days. Formula: n × d = 180 or d = 180/n.